NS Rail CTW300 Project (KSA)

Project Description

Design, development, installation and operational optimisation of 1100tph rail ballast and aggregates plant to service and supply 2.25Mt rail ballast for 820km rail construction in remote location within the Kingdom of Saudi Arabia (KSA), comprising:

  • Twin 550tph Primary crushing stations
  • Surge Pile and recovery system
  • Triple HSI Secondary / Tertiary crushing station incl 150t surge bin
  • Twin control screens
  • Final aggregate screen producing -20mm aggregates for concrete rail sleeper pre-cast plant
  • Field conveyor and radial stacker system for 300kt ballast stockpile servicing rail load-out
  • On-site diesel power generation
  • Switch-room / MCC / Control Room
Scroll to top